A-015 · China Harbour – Agility Consortium
Bridges 7 & 8, Reem Island – E12
Al Reem Island, Abu Dhabi
Two bridges linking Reem Island with Sheikh Khalifa Bin Zayed Highway (E12).
- Contract value
- AED 377M
- Start
- Jul 2023
- Completion
- Feb 2026
- Duration
- 32 months
- Status
- Completed
- Client
- Bunya Enterprises
- Employer
- Bunya
- Consultant
- Parsons
- Contractor
- China Harbour – Agility Consortium
Scope of work
- Cast-in-place box girder bridges and all associated works
- Pedestrian walkways and cycle paths
- MSE walls and retaining walls
- Utilities bridge and Transco pipeline culvert
- Landscaping, irrigation, lighting and utilities
Gallery
In the news
Contract title
Construction of Bridges 7 & 8 between Reem Island and Sheikh Khalifa Bin Zayed Highway (E-12), Abu Dhabi (Bridges7&8/9.3/CON/2023/040)
Related projects
Completed 2019–2023
Mina Zayed Tunnel
About 2.5 km of new road network with tunnels, a flyover and underpasses in Mina Zayed.
Musanada AED 1.65B
Completed Dec 2023
View project details
Photo: Abu Dhabi Media Office Completed 2020–2022
East–West Baniyas Interchange
Interchange linking East and West Baniyas, with movements in all directions to and from Abu Dhabi and Al Ain.
Department of Municipalities and Transport (Abu Dhabi City Municipality) AED 218M
Completed Nov 2022
View project details
Photos on completion
Ongoing 2024–2027
Bloom Living – Ring Roads & Infrastructure
Ring roads, core infrastructure and conversion of Junction E01 at Bloom Living, Zayed City.
Bloom District Properties AED 200M
Contract time elapsed90%
2024.092027.01
View project details